Industrial
Case Study Project Synchro 2, Gloucester
The project involved extension to existing building which entailed connections into the existing building, maintaining the full operation of the existing facility.
The extension covered a 8236m2 area, with cladding and composite clad panels. The building has a full sprinkler system and incorporated doc levellers. The cold store has been constructed to operate at +2o.
The project also involved extension to the existing hard standing and roads.


Project Manager
Tuffin Ferraby & Taylor
16 Queen Street
Bristol
BS1 4NT
Architect
The Bush Consultancy
Bush House
72 Prince Street
Bristol
Value - £4,655,000
Contract Period - 37 weeks
Contract Type - JCT with contractors design
Area - 8236 m2