Case Study Clark’s Project Westway, Street, Somerset
The works comprised the construction of a new national distribution facility with associated office accommodation for Clarks shoes.
The steel framed structure is on mass concrete foundations with dock leveller pits of precast concrete.
In order to achieve early enclosure of the building facing brickwork to ‘Quick Wall’ precast concrete units was introduced at low level. Elsewhere the envelope is of flat composite panels and curtain walling.
The aluminium roof sheets were rolled on site and at 150 metres were, at the time, the longest installed in Europe.


Project Management
Arup
63 St. Thomas Street
Bristol
BS1 6JZ
Architects
Atkins Walters & Webster
25 King Square
Bristol
BS2 8JN
Value - £20,000,000
Contract Period - 69 weeks
Contract Type - JCT 1998 Editions with Quants
Area - 330,000 sq ft